If you only look at numeric preservation codes (10 through 55), you can miss high-risk two-letter Table J-Ia codes—and miss critical solicitation text stacked right underneath them.
Here is how Method GX works in practice, walked through DLA Weapons Support (Columbus) RFQ SPE7M1-27-T-2703 (issued November 17, 2026) for NSN 5962-01-166-8405 (Linear Microcircuit, FSC 5962, citing Microsemi Corp. Analog Mixed Signal CAGE 34333 P/N SG7915ACP).
What Is Method GX Under MIL-STD-2073-1E?
Under MIL-STD-2073-1E (Change 4, Table J-Ia), Method GX is a specialized electrostatic discharge (ESD) and electromagnetic interference (EMI) protection procedure built around Method 41 (heat-sealed watervaporproof barrier protection) paired with strict ESD/EMI controls.
In general Method GX terms, items are handled under an ESD control program, wrapped or cushioned with ESD-compatible materials (such as MIL-PRF-81705 Type III / MIL-DTL-117 Type II Class H Style 2 or MIL-DTL-81997 Type I cushioned pouches where applicable), and unit-packed in a heat-sealed MIL-DTL-117 Type I, Class F, Style 1 barrier bag while protecting leads and terminals from mechanical stress and applying MIL-STD-129 ESD caution markings.
Reading RFQ SPE7M1-27-T-2703 (NSN 5962-01-166-8405)
On pages 8–9 of SPE7M1-27-T-2703 (CLIN 0001, PR 7018675838, 225 EA, 129 DAYS ADO, 0% plus/minus quantity variance, destination inspection and acceptance at DLA Distribution DDWO in Columbus, OH), the solicitation spells out the packaging string and layers extra microcircuit and ESD rules right below it:
Section B Packaging Block (SPE7M1-27-T-2703)
- PKGING DATA:
MIL-STD-2073-1E| QUP:001| PRES MTHD:GX - CLNG/DRY:
1| PRESV MAT:00| WRAP MAT:ZZ| CUSH/DUNN MAT:ZZ| CUSH/DUNN THKNESS:C - UNIT CONT:
ZZ| OPI:M| INTRMDTE CONT:D3| PACK CODE:U| INTRMDTE CONT QTY:AAA - MARKING:
MIL-STD-129| SPECIAL MARKING CODE:ZZZZ(Special Requirements)
If you want to see what each code in this string means, run it through our free MIL-STD-2073-1E Packaging Code Decoder.
Here is an overview of the key packaging instructions, step-by-step procedures, and compliance clauses found in RFQ SPE7M1-27-T-2703:
Key Quality and Packaging Instructions
- QPL-81705 ESD/EMI Rules: Requires DoD-qualified protective bags from a QPL-81705 manufacturer processed at an approved workstation.
- Cushioning Specifications: Specifies
A-A-59136, Class 1, Grade Bcushioning (1.7–2.2 lb/cu ft) with a thickness at least1/8 inchgreater than component lead length. - Lead Finish Marking: Requires
IPC/JEDEC J-STD-609terminal finish attributes placed on individual unit packs alongsideMIL-STD-129labels. - QSLD/QTSL & Form 918 Gates: Governed by Procurement Note
M01andDLAD C03for FSC5962microcircuits, requiring DLA Form 918 and unredacted traceability/test data submitted toMaritime.CDAP.Monitor@dla.milat least 15 days prior to delivery. - Competition & Clauses: Unrestricted competition, destination inspection, FOB Origin, strict mercury bans, CMMC Level 2 (
RD004), and WAWF invoicing (DFARS 252.232-7006).
Step-by-Step Guide: Packaging Microcircuits Under Method GX
Preparing, packing, and labeling the 225 units of Microsemi P/N SG7915ACP (NSN 5962-01-166-8405) involves setting up an approved ESD workstation, cleaning/drying components (CLNG/DRY: 1, PRESV MAT: 00), wrapping in static-dissipative material (MIL-PRF-81705, Type III) with proper cushioning, sealing inside a converted MIL-PRF-81705, Type I barrier bag (Method GX), applying MIL-STD-129 and J-STD-609 markings, and packing into intermediate and exterior shipping containers (INTRMDTE CONT: D3, PACK CODE: U).
Step 1: Set Up an Approved ESD Workstation
- Requirement: All handling and packaging must take place at an approved field-force protective workstation.
- Material Verification: Ensure all barrier bags and wraps are sourced from a qualified manufacturer currently listed on QPL-81705.
Step 2: Clean, Dry, and Protect the Leads (QUP: 001)
- Quantity per Unit Pack (QUP): Pack 1 microcircuit per individual unit pack (
QUP: 001). - Cleaning & Drying (
CLNG/DRY: 1): Ensure the component is clean and dry before wrapping; no preservative coating is required (PRESV MAT: 00). - Lead Immobilization & Cushioning:
- Wrap the part in MIL-PRF-81705, Type III (MIL-DTL-117, Type II, Class H, Style 2) static-dissipative barrier material.
- Apply A-A-59136, Class 1, Grade B cushioning (density between 1.7 and 2.2 lbs/cu ft). The cushioning thickness (
CUSH/DUNN THKNESS: Z) must be at least 1/8 inch thicker than the length of the component's leads to prevent bending or puncturing. - Alternative: You may place the component in an ESD-protective, form-fitting container that immobilizes and maintains the original lead configuration, supplemented with anti-static cushioning.
Step 3: Seal the Unit Pack (Preservation Method GX)
- Outer Unit Bag: Place the wrapped and cushioned component inside a converted barrier bag conforming to MIL-PRF-81705, Type I (MIL-DTL-117, Type I, Class F, Style 1) for combined ESD and Electromagnetic Interference (EMI) protection.
- Heat-seal the bag completely.
Step 4: Apply Unit Pack Markings
Every single unit bag (all 225 of them) requires two sets of markings:
- Standard Military Markings (
MIL-STD-129): Include the NSN (5962-01-166-8405), CAGE Code (34333or authorized source), Part Number (SG7915ACP), Quantity (1 EA), Contract Number, Method of Preservation (GX), Date of Preservation, and ESD sensitivity labels. - Lead Finish Marking (
IPC/JEDEC J-STD-609): Apply the assigned terminal finish attribute code (e.g.,e0for leaded ore1–e7for Pb-free) per paragraphs 5.3.1–5.3.2, placed clearly on the exterior of the unit pack per paragraph 6.2.
Step 5: Pack into Intermediate & Exterior Containers
- Intermediate Container (
INTRMDTE CONT: D3): Group the individual unit packs into rigid fiberboard intermediate boxes (D3). (Note: Intermediate container quantity isAAA—follow standard MIL-STD-2073-1E limits so unit packs aren't crushed). - Exterior Shipping Container (
PACK CODE: U): Pack the intermediate containers into a standard commercial/military exterior shipping carton (Pack Code U) suitable for safe transit to DLA Distribution DDWO (Columbus, OH). - Pre-Shipment Traceability Packet: Remember that at least 15 days prior to delivery, you must email DLA L&M Form 918 and unredacted supply chain traceability/test reports to
Maritime.CDAP.Monitor@dla.mil. Once approved in writing, place a paper copy of Form 918 and the written authorization inside the shipping package for each lot.
The finished unit container should look similar to this one below:

Why Method GX & Special Clauses Can Make or Break a Quote
Vendors must maintain strict compliance to avoid frequent packaging and labeling discrepancies penalized under DLAD Procurement Note C14, while tracking RFID rules, IUID mandates, and a mandatory six-year chain-of-custody retention window (DLAD C03).
Quoting a complex DLA solicitation withMethod GX,QSLD/QTSL(M01), orForm 918traceability rules? Book a 60-minute DLA & DIBBS Strategy Call ($498) with an activeCAGE: 09D43contractor to validate your compliance and bid strategy.
Free Resources & Next Steps
Use free tools including local APEX Accelerators, DLA's RP001 / master TQ list, the MIL-STD-2073-1E Packaging Code Decoder, and the Methods of Preservation Guide.
Note: Informational GovCon and packaging analysis based on RFQ SPE7M1-27-T-2703 and cited standards. Always verify exact solicitation clauses, revisions, and drawings before bidding or shipping.